The Podilskyi plant builds a concrete access road and areas

At the end of May, Podilskyi Cement had a special celebration of opening the access road from the Khmelnytskyi Highway H-03 to the weighbridge and the concreted areas of cement dispatching terminals Nos. 2 and 3.  

The construction had taken 3 months: from November to April. The road surface and the surface of the industrial sites have been completely restored, and the road has been widened at the place where cement trucks wait to be loaded.  

The road was built using B30 fiber concrete on the basis of AS-500 cement with special Macro Synthetic Fiber additives, as well as using В7,5 concrete. The total area concreted for this project is 27,857.0 m2. 

We use cookies to make this site work and help us make improvements to ensure you the best user experience. By clicking "Agree", you confirm your consent to the use of this technology. You can find more information about the cookies that we use on our PRIVACY page. If you do not agree to our use of cookies, please adjust your browser accordingly or do not use the site cemark.ua.

Agree